May 3, 4 and 5th
I flew down and visited the boat May 3rd. First time I could see it
on the hard in St Augustine.
Bumpers and mooring lines were still left out and the boat
needed
some attention, so it is good to come down soon after the boat is
hauled out. Slept over on it 3rd and at
the end of the day on the 4th, headed to Orlando so I had a safer
spot
for my flight back. I also ran fresh water through the
engines and then anti freeze as a corrosion protection measure. I
put
the name on the stern that
Cheryl designed, moved the dingy
below the boat,
and put the
engine on a stand. I also wrestled the main into the cabin and got
it
out of the weather. I taped up all the through hull areas and met
with
the fiberglass guy to discuss the work needed. I fired this work up
when I got home and it was done by the end of May. Also signed
off on hurricane straps. If that was not enough, I reworked the
cushions to get them all out of the way, and dropped the anchor and
chain down to keep the tarp down and allow me to measure the chain
(It
is shorter than they said :-). It is 130 feet in total, which
I think I can work with.
July 7, 2017
I fly out early again (leave at 4am from home), and get to Orlando
on
time. First stop is the St John's county tax collector where we
square
up on sales tax and get the boat registered. They needed Cheryl's
Drivers License and signature which made things more interesting,
but
we got it sorted.
When I got to the boat I noticed my swim ladder was missing. Found
that
in the welding shop. Also got a estimate list for the repairs we
wanted
done, not sure where it got hung up. The fiberglass work looked OK,
they could have done a few things better, but it will work. I took
some
of the salon cushions to the Irish Sail lady and the Genoa. Hot day
and
I was sweating pretty good... Glad we will sail in the winter :-)
July 8, 2017
Fitted the helm enclosure and
marked what was broken, brought it to the
Irish Sail lady as well, with the rest of the salon cushions. Re
wrapped the head stay, and rolled up the furler line. Noticed a birds
nest in the cockpit shades so I took them down, washed them and stowed
them below.
Also drilled and mounted the seagull
water filter. Measured the anchor
chain, tested the deck hatches (all seem fine except the two aft
ones
over the bunks.) Did some sorting and cleaning. It was a very hot
day,
but a welcome rain storm came in around 4:30 and cooled things down
some.
At the end of the day I pushed on the hurricane straps, they came
right
out of the ground,
tried the other three, all were easy to pull out,
they were only in one turn. Most boat look like that, so the straps
are
a joke at best... Told the yard manager.
July 9, 2017
Fixed the seagull
plumbing as the pipe was leaking and would leak a
good deal if pulled around. Cut the tube shorter and tried to be
more
square. Also put the tube in deeper in the "T" fitting. This seems
to
have fixed the issues. Measured the mainsail cover and all the
hatches.
Made list of what needs to be replaced and will start work on
sourcing
those parts. Boat looks a little empty/torn up, but it
does not
seem to be suffering in dry dock so far.
Sept 14th, 2017
I fly down three days after IRMA smashes Florida to check on things.
My
timing is pretty good as my original flight, booked two months
earlier,
would have had me landing in Orlando right as Irma was visiting the
same area... The boat looks fine at first glance, but there are some
odd items. The biggest concern is the dingy and the key jack stand it was chained to are
now behind the boat.
At first I assume this is from the wind, but the jack stand has been
lowered and the bottom sanded, so the yard workers moved the dingy
and
jack stand before the storm to prep the bottom and simply never
moved it
back. Very careless, but typical of boat yards everywhere as near as
I
can tell.
I moved the dingy and put the jack stand back where it belonged. I
mentioned it to the yard manager, but I do not think they really
care,
so I need to track this on my own. The stern jack stands were oil
canning the far aft end of the swim steps and I loosened these two
jack
stands to solve this problem. The bow jack stands were loose, so the
boat had settled a little stern down. I need to be more aggressive
at
adjusting these stands going forward as the yard does not check
them.
The good news is the bottom prep
seems very good,
and they will put epoxy barrier coats on all exposed gel coat before
painting so this should look good. The sail drives have been painted and boot seals installed.
The boat also seem to have picked up a lot of black mold on
any
plastic/vinyl surface like winch handle holders or fiberglass trim
work. Must be from the summer humidity and all the rain. The hatches
above each bunk also leaked from the driving rain in the high
winds. 6
mono hulls tipped over in the wind which is about 20% of the total
number of mono hulls in the yard, and a few hurricane straps pulled
out
(I think these are mainly useless as the yard does not set them in
the
ground far enough to be of any value), but otherwise things were
OK. Had to sponge standing water out of the Port Bow cabin. A
good thing was, despite being unsecured, the dingy did not go
anywhere
in the breeze and seemed undamaged.
I met up with the canvas folks in the yard, and agreed on new
cockpit cushions. Also cleaned
up some of the mold and and wiped up any water down below.
Sept 15th.
I had a late afternoon flight out of Orlando so it was a short day,
but
I did charge the house and engine batteries some and put on the new hatch covers Cheryl had
made. I also aired things out
and picked up the new sail cover, and rub rail for the stern. I
installed the new toilet seats and dried all the bilges. I noticed
oil
in the bilge water of the engine compartments, I dropped an email to
the mechanic about this. My guess is it is just from the service
work,
but worth checking. Sweated like a dog and then headed home!
Oct 1, 2017
Took the nice 6am flight out of Milwaukee but to Jacksonville this
time. Short stop in Atlanta resulted in roughly the same travel time
as
the previous flights direct to Orlando. The big jobs for this trip
were
to pick up the helm station
canvas
and the Genoa from the Irish Sail lady and I also got one of the
cabin
cushions back. With some effort, I was able to get the dingy back on
the davits. This will get it out of the way when they paint the
hull.
I also test fit the new cockpit
cushions, and helm seat
which look good, and took everything off so it would not get dirty.
It had rained a good deal the previous two weeks, and all four
hatches had leaked some. Two bow cabins seemed the worst. Not as bad
as after the hurricane, but still not good. I decided to cut covers
for the hatches from a Tarp, to protect them from the sun as well as
provide a seal to keep any leaks from the hatches themselves. The
logs do not mention hatch leaks anymore, so maybe this does the
trick!
Oct 2, 2017
Met up with the canvas guy on the bunks. He recommended I break the
zippers which were rusted solid, and wash
the covers. The foam seemed OK, so this was the evening
project. Hot work, but most of
the covers seem good. Cheryl will decide in November on their final
fate!
I also agreed to him building a dingy cover so the dingy can hang on
the davits and still be protected from the Florida sun.
I also re blocked the stern of the boat as there was a jack stand
under
each transom that was oil canning the hull some there. Took these
out
and found jack stands that fit under the hull in more solid spots to
replace them.
Oct 3,
Headed out to visit Mary and Jim near Tampa. Had good visit with
each of them. Jim passed away a few weeks later, so it is good I was
able to re-connect with him.
Nov 6th
Headed out with a full load of gear
to bring to the boat and get the refit done. Took a few days to
drive down and passed my USCG Captains test on the way down.
Nov 9th
Arrived in St Augustine and picked up my brother John who was on his
boat in the St Augustine harbor. With John's
help, we unpacked the truck and replaced the three tired 4D house
batteries with nice new LifeLine units. The move to Tab connectors
added some to
the project as the old automotive connectors were hard to get off,
but
by the end of the day, the work was mostly done. Also installed the
Link battery monitor at this time to take advantage of the batteries
being disconnected. No notes on any water issues, so I think my tarp
hatch covers worked.
Nov 10th
John helped once again and we removed the beat up and damaged stern
rub
rail and did some clean up on the battery installation. I also
picked
up the cabin salon cushions from the Irish Sail Lady. They look good
and I just need to put the locking boards in on the bottoms of the
cushions to hold them in place. That afternoon I put epoxy in all
the
old rub rail screw holes, and also filled in some voids in the
laminate
at the edges to clean up the hull joint for the new rub rail.
Nov 11th Saturday
John took the day off and I installed
the new rub rail. I also installed the new cockpit hatch
screen. The New 80lb Mantus anchor was put on the chain, the anchor chain marked and 40 feet of
5/8" rode added and spliced in and the new anchor was hoisted into position.
A fairly productive day.
Nov 12th
Based on the trouble our neighbors behind us were having with their
engines, I decided to try an start each engine. Got two out of three
running. After buying a new engine start battery, the issue turned
out
to be the starter on the Port engine. This is being replaced by the
local mechanic and I will also pick up a spare. I put in the new
speedo/depth unit and ran the starts of a NEMA 2000 bus for the new
instruments. Spend a good deal of time organizing all the spares and
supplies into plastic containers and stowing them in the port bow so
the boat was in better shape for Cheryl.
Nov 13th
Cheryl's flight arrived on time and John returned to help with the
projects which included putting the name
on the bows
(note the old batteries off the boat as well), and re-striping the
hull
to remove the Moorings paint colors. As with most tasks, this one
took
longer than expected and the fairly stiff winds did not make the job
easier.
Also started on the radar installation on the mast, with the big
goal
for the day of getting the radar cable installed in the mast and
into
the boat. This sounds easy, but with our approach, it took much of
the
day!
Nov 14th.
We met up with the canvas shop folks at the yard and agreed the plan
for the new bunks and which covers needed replacements. Also
finished
the striping and name work and mounted the radar support as well as
the
radar dome itself on the mast. We
jury rigged the electrical connections for everything and fired up
the
radar, speedo and display. It all worked which is very nice!
The
Mechanic also visited and quickly decided the starter motor was no
good
and will replace it next week.
Nov 15th
Clean up time and we used the day to clean some areas inside and
outside the boat as well as make final choices on the new bunk foam
and
covers. John joined us once more and we made some progress running
the
SSB ground planes and NEMA 2000 bus wires through various hidden
areas
of the boat. Also fired up the Starboard engine once more to be
happy
it will start in January. Since we had some issues, I will make one
more trip down in December to verify things before we launch. Don't
want to be sitting in a broken down boat after driving to Florida!
With a fairly successful week of work, and thanks to great help from
John and Cheryl, we are in very good shape for launching. There are
still many projects to work on once we launch like installing the
new
hatches and screens, and installing the AIS and instruments, but we
have made good progress and all jobs that needed outside vendors are
done as well as all jobs that had to be done out of the water. The
refit over the summer is basically complete which feels great. When
you
look at the prep work on the
hull, and before and after shots of the rub rails
you can see the progress. A close
look at the bows with a couple
of before and after shots
shows how much work was done
on the fiberglass and gel coat repairs and bottom work.
Nov 16 and 17
Broke the drive back into 2 days. It is about 1300 miles and I did
850 of it the first day, so the second day was not too bad.
Dec 19 and 20th
Flew down to make sure engines worked, and to get a few more
projects
done. Added a registration plate to Dingy (Glued on), took off
mainsail
cover, put on the Genoa, added a wedge to the radar dome mount so it
was
more horizontal, and asked the yard to fix and re-glass a crack on
the
port stern that had been flagged in the survey. Short trip, with 6am
flights each day.